Time-Lapse
Demolition of original house (Aug 4-7, 2014)
Street view:
Rear view:
Demolition and removal of original foundation (Aug 20-21, 2014)
Street view:
Rear view:
Staking out for the new foundation (August 26, 2014)
http://vimeo.com/106074242
Bye Bye trees… (August 29 & September 3-4, 2014)
Digging the hole for the new foundation (September 10-11, 2014)
Street view:
Rear view:
Footings and foundation (September 29 – October 4, 2014)
Backfill (October 16-17)
Framing – 1st and 2nd floors (October 20-31)
Framing – Roof (November 3-14)
Skirt and Soffits (November 14-22)
Septic, Drywells, & Water Line (November 25, December 1-2)
Roof Shingles and Trim (December 2-16)
Tyvek and Windows (December 16-19, 30-31)