Foundation

September 29-30, 2014

P1080328The footings form the base of the foundation. Here the guys installed the wooden frames for the footings, which are 2′ wide and 1′ deep.

 

P1080339

 

 

 

The next day, Suffolk Cement showed up to fill the wooden frames with concrete.  They needed to use a long nose to reach the corners of the house.

 

P1080346

 

They stepped up the footings in some places. The depth of the footings depended on how far they needed to dig to reach virgin ground.

 

 

P1080342

There are also some lolly columns on the ground level to support the house.  Here he’s filling the footings for the lolly columns. In the end, it took 2 trucks of concrete for the footings. I think it was 14 yards.
P1080356

 

And then he adds the “key” that holds the foundation on top of the footings. Amazing that’s all it takes.

 

 

 

P1080359

 

And now it’s done.  It dried for one day before they set the forms for the foundation.

 

 

 

 

October 1-4, 2014
P1080379They brought the forms for the foundation the next day.

 

 

 

 

P1080383

 

 

The forms went up pretty fast. They were 9 feet tall.

 

 

 

P1080414

 

Here you can see the side view of the frames. The thickness of the walls is 10 inches. You can see the steel cross bars.  They also put rebar along the lengths of the walls since they were so tall.

 

 

P1080396

 

Since there are windows and a door on the ground floor, they made wooden frames that fit between the forms.

 

 

 

P1080392And then they dropped them down between the forms. How in the world did they know where to put them?

 

 

 

P1080408
After the forms were done, they surveyed the height of the forms to determine how high to fill the concrete.  Then they made a red chalk line inside the forms — about 2 inches from the top.

 

 

P1070311The next day the monster pump truck showed up to fill the forms with concrete. It was a giant blue crane with a hose that could deliver the concrete to all the corners of the house.

 

 

P1080441The concrete truck would back up to the pump truck to transfer the concrete. It took four trucks of concrete plus a little extra for the whole foundation. It was something close to 40+ yards of concrete.

 

 

P1070301

Here they are filling the forms with concrete from the snout of the pump truck.

 

 

P1070315

 

 

Once filled, they smoothed the concrete and placed the bolts that attach to the silt plate of the house.

 

 

My beautiful picture

 

 

They came back to remove the forms the next day.

 

 

My beautiful picture

 

 

 

Two days later, they came back with another crane to take away the forms.

 

 

 

My beautiful picture

 

 

And they painted black waterproofing tar on the foundation where it will be backfilled with dirt.

 

 

P1080477

 

Done!

 

 

 

 

P1080488

 

Here I am — inside the ground floor of the house for the very first time.

 

 

 

 

Photo Journal

  • In the Beginning
  • Demolition
  • Bye Bye Trees
  • Excavation
  • Foundation
  • Backfill
  • Framing – 1st Floor
  • Framing – 2nd Floor
  • Framing – Roof
  • Sheathing, Strapping, & Skirt
  • Septic, Drywells, & Water Line
  • Roof, Trims, & Tyvek
  • Windows and Decks
  • Exterior Insulation & Trims
  • Oh, what a winter…
  • Decks and Siding
  • Buried Electric & Garage Door
  • Plumbing, Electric, & HVAC
  • Underground Propane Tank
  • Walkway & Interior Stairs
  • Insulation & Sheetrock
  • Finishing

Copyright 104 Cliff Road East 2025 | Theme by ThemeinProgress | Proudly powered by WordPress