Time-Lapse

Demolition of original house (Aug 4-7, 2014)
Street view:

Rear view:

 

Demolition and removal of original foundation (Aug 20-21, 2014)

Street view:

Rear view:

 

Staking out for the new foundation (August 26, 2014)
http://vimeo.com/106074242

 

Bye Bye trees… (August 29 & September 3-4, 2014)

 

Digging the hole for the new foundation (September 10-11, 2014)

Street view:

Rear view:

 

Footings and foundation (September 29 – October 4, 2014)

 

Backfill (October 16-17)

 

Framing – 1st and 2nd floors (October 20-31)

 

Framing – Roof (November 3-14)

 

Skirt and Soffits (November 14-22)

 

Septic, Drywells, & Water Line (November 25, December 1-2)

 

Roof Shingles and Trim (December 2-16)

 

Tyvek and Windows (December 16-19, 30-31)

 

Photo Journal

  • In the Beginning
  • Demolition
  • Bye Bye Trees
  • Excavation
  • Foundation
  • Backfill
  • Framing – 1st Floor
  • Framing – 2nd Floor
  • Framing – Roof
  • Sheathing, Strapping, & Skirt
  • Septic, Drywells, & Water Line
  • Roof, Trims, & Tyvek
  • Windows and Decks
  • Exterior Insulation & Trims
  • Oh, what a winter…
  • Decks and Siding
  • Buried Electric & Garage Door
  • Plumbing, Electric, & HVAC
  • Underground Propane Tank
  • Walkway & Interior Stairs
  • Insulation & Sheetrock
  • Finishing